MVP1 Ready for Testing Status
A manually updated dashboard showing overall “Ready for Testing” status for MVP1. This is intentionally high-level. For details see Jira, Practitest, Detailes Test Reports, or ask on Slack (#testing, or one of the Scrumt Team channels)
If info here does not match what you believe is the case, what you see in Jira etc. (and the difference can’t be accounted for by the “last updated” timestamp, please have a conversaton with @Diarmid Mackenzie or @Adam Leon Smith as this suggests a comms gap.
Colour coding is highly subjective, but roughly: green = on track, amber = off track, but with a correction plan in place, red = off track & no clear plan, grey = descoped
Link to MVP1 spreadsheet
Link to JIRA
Last updated: 11 June, 10am Eastern
MVP Story | Overall Status | Action needed |
---|---|---|
MVP1: GPS logging gaps | More-or-less done on Android. iOS with Guam Dev. No clear date/plan for iOS yet. | Clear iOS plan from Guam. Now capturing locations, but data not going into Realm yet. Further update promised 6/12 - now overdue. Diarmid to chase in tf_gps-accuracy channel. Also could try Rahul @ Intel. |
MVP2: GPS accuracy | Deferred to Mercury - though there has been Android progress under MVP1. |
|
MVP3: Encryption on device | Implemented and mostly tested |
|
MVP4: Clarify limitations via copy | Ready for Test as of 6/14 |
|
MVP5: Feature Flags | Implemented, tested, all good. |
|
MVP6: Clarify Exposure Notification | With Rocket. SAF-283/SAF-284. Was due to be R4T by 6/11. | Vlatko working on this for 6/16. |
MVP7: Auto-subscription | In develop as of 6/14, but I’ve been told by @Jacob Jaffe (Deactivated) that it is not working. | Going to be de-scoped. |
MVP8: Improved user consents | Ready for Test. No blockers. |
|
MVP9: Internationalization | Lots of work still in Progress - no clear date for delivery into test. | Get clear plan from Alpita. Waiting for stable English app copy. Jen is chasing with Ali. |
MVP10: Designate Privacy Policy in Settings | Ready for Test. | |
MVP11: Safe Places UX | About 80% Ready for Test. I’m assuming there is a plan for the remaining 20%? (214, 327, 331, 332) | Get clear plan for 4 remaining TO DOs (all with David - awaiting firm completion plan) Now aiming for 6/18. Jen working to see if we can get another FE Dev. |
MVP12: Manually enter points as CT | R4T now with one small fix to come later today(end- time → duration) |
|
MVP13: Load, edit, save aggregated data | Ready for Test. |
|
MVP14: Configure Retention Policy | Ready for Test. |
|
MVP15: Publisher Tool | Ready for Test |
|
MVP16: Secure transmission of location data | Ready for Test | |
MVP17: Scalability | Pagination & Hashing App code now merged, but JJ says still some connecting code missing. Also still missing “HA by URL” function | JJ actively working on this. |
MVP18: Encryption of Points of Concern | This function is ready, but can only be tested with MVP17 | As per MVP17 |
MVP19: Efficacy measurement | Descoped |
|
MVP20: Tunable GPS intersection logic | This function is ready, but can only be tested with MVP17. Agreed PLACES-80 is out of scope. | As per MVP17. |
MVP21: Onboarding flows for HAs | Descoped. |
|
MVP22: Safe Paths → PathCheck | R4T |
|
MVP23: Rework HA YAML file | SAF-400. Will deliver alongside MVP7. | Jacob’s top priority - to deliver by end of day. |
MVP24: Tab redesign | SAF-479. Ready for Test |
|