A manually updated dashboard showing overall “Ready for Testing” status for MVP1. This is intentionally high-level. For details see Jira, Practitest, Detailes Test Reports, or ask on Slack (#testing, or one of the Scrumt Team channels)
If info here does not match what you believe is the case, what you see in Jira etc. (and the difference can’t be accounted for by the “last updated” timestamp, please have a conversaton with Diarmid Mackenzie or Adam Leon Smith as this suggests a comms gap.
Colour coding is highly subjective, but roughly: green = on track, amber = off track, but with a correction plan in place, red = off track & no clear plan, grey = descoped
Link to MVP1 spreadsheet
Link to JIRA
Last updated: 11 June, 10am Eastern
MVP Story | Overall Status | Action needed |
---|---|---|
MVP1: GPS logging gaps | More-or-less done on Android. iOS with Guam Dev. No clear date/plan for iOS yet. | Clear iOS plan from Guam. Now capturing locations, but data not going into Realm yet. Further update 6/12. |
MVP2: GPS accuracy | Deferred to Mercury - though there has been Android progress under MVP1. | |
MVP3: Encryption on device | Implemented and mostly tested | |
MVP4: Clarify limitations via copy | Status not clear: MVP spreadsheet suggests MVP4 descoped. Yet we have SAF-466 in progress, still not yet in test, and not tracked in an MVP Epic. | Clarify status & tracking of MVP4. |
MVP5: Feature Flags | Implemented, tested, all good. | |
MVP6: Clarify Exposure Notification | With Rocket. Should be R4T by 6/11. | |
MVP7: Auto-subscription | Nearly ready - will be available in a bespoke APK 6/11, should be in develop by 6/12. | |
MVP8: Improved user consents | Ready for Test. No blockers. | |
MVP9: Internationalization | Lots of work still in Progress - no clear date for delivery into test. | Get clear plan from Alpita. Waiting for stable English app copy. |
MVP10: Designate Privacy Policy in Settings | Ready for Test. | |
MVP11: Safe Places UX | About 80% Ready for Test. I’m assuming there is a plan for the remaining 20%? (214, 327, 331, 332) | Get clear plan for 4 remaining TO DOs (all with David - awaiting firm completion plan) Probably 6/12 or later |
MVP12: Manually enter points as CT | SAF-496 “duration” still outstanding | Get plan on SAF-496 Satoshi work is done |
MVP13: Load, edit, save aggregated data | Ready for Test. | |
MVP14: Configure Retention Policy | Ready for Test. | |
MVP15: Publisher Tool | Ready for Test | |
MVP16: Secure transmission of location data | Ready for Test | |
MVP17: Scalability | Pagination & Hashing App code now merged. Still missing “HA by URL” function | Main PR merged. No plan yet for HA by URL |
MVP18: Encryption of Points of Concern | Comes along with MVP17 | As per MVP17 |
MVP19: Efficacy measurement | Descoped | |
MVP20: Tunable GPS intersection logic | Comes along with MVP17. Agreed PLACES-80 is out of scope. | As per MVP17. |
MVP21: Onboarding flows for HAs | Descoped. | |
MVP22: Safe Paths → PathCheck | Under implementation with Yonatan. | Blocked on info from Ali. Also Splash Screen need to be redesigned. 6/15, 6/16. |