A manually updated dashboard showing overall testing “Ready for Testing” status for MVP1. This is intentionally high-level. For details see Jira, Practitest, Detailes Test Reports, or ask on Slack (#testing, or one of the Scrumt Team channels)
If info here does not match what you believe is the case, what you see in Jira etc. (and the difference can’t be accounted for by the “last updated” timestamp, please have a conversaton with Diarmid Mackenzie or Adam Leon Smith as this suggests a comms gap.
...
Link to MVP1 spreadsheet
Link to JIRA
Last updated: 10 11 June, 9am 10am Eastern
MVP Story | Overall Status | Action needed | ||||
---|---|---|---|---|---|---|
MVP1: GPS logging gaps | More-or-less done on Android. iOS with Guam Dev. No clear date/plan for iOS yet. | Clear iOS plan from Guam. Now capturing locations, but data not going into Realm yet. Further update promised 6/12 - now overdue. Diarmid to chase in tf_gps-accuracy channel. Also could try Rahul @ Intel. | ||||
MVP2: GPS accuracy | Deferred to Mercury - though there has been Android progress under MVP1. | |||||
MVP3: Encryption on device | Implemented and mostly tested | |||||
MVP4: Clarify limitations via copy | Status not clear: MVP spreadsheet suggests MVP4 descoped. Yet we have SAF-466 in progress, still not yet in test, and not tracked in an MVP Epic. | Clarify status & tracking of MVP4Ready for Test as of 6/14 | ||||
MVP5: Feature Flags | Implemented, tested, all good. | |||||
MVP6: Clarify Exposure Notification | Scope & status unknown - no update since 29 May | Get clear plan from GuamWith Rocket. SAF-283/SAF-284. Was due to be R4T by 6/11. | Vlatko working on this for 6/16. | |||
MVP7: Auto-subscription | Scope & status unknown - no update since 5 June | Get clear plan from GuamIn develop as of 6/14, but I’ve been told by Jacob Jaffe (Deactivated) that it is not working. | Going to be de-scoped. | |||
MVP8: Improved user consents | Ready for Test. No blockers. | |||||
MVP9: Internationalization | Lots of work still in Progress - no clear date for delivery into test. | Get clear plan from Alpita. Waiting for stable English app copy. Jen is chasing with Ali. | ||||
MVP10: Designate Privacy Policy in Settings | Ready for Test. | |||||
MVP11: Safe Places UX | About 80% Ready for Test. I’m assuming there is a plan for the remaining 20%? (214, 327, 331, 332) | Get clear plan for 4 | x remaining TO DOs (all | currently unassigned)with David - awaiting firm completion plan) Now aiming for 6/18. Jen working to see if we can get another FE Dev. | ||
MVP12: Manually enter points as CT | SAF-496 “duration” still outstanding | Get plan onf SAF-496 from Satoshi | R4T now with one small fix to come later today(end- time → duration) | |||
MVP13: Load, edit, save aggregated data | PLACES-127 still to do. | Get clear plan on PLACES-127 (unassigned - so talk to Dan McCoy?)Ready for Test. | ||||
MVP14: Configure Retention Policy | Ready for Test. | But we need a decision on SAF-469. I’m assuming out of scope. Will be green when we make that decision.Agree to descope SAF-469 | ||||
MVP15: Publisher Tool | Ready for Test | |||||
MVP16: Secure transmission of location data | Ready for Test | |||||
MVP17: Scalability | Pagination & Hashing App code | still not merged.Get plan for thisnow merged, but JJ says still some connecting code missing. Also still missing “HA by URL” function | JJ actively working on this. | |||
MVP18: Encryption of Points of Concern | Comes along This function is ready, but can only be tested with MVP17 | As per MVP17 | ||||
MVP19: Efficacy measurement | Descoped | |||||
MVP20: Tunable GPS intersection logic | Comes along with MVP17This function is ready, but can only be tested with MVP17. Agreed PLACES-80 is out of scope. | As per MVP17. | ||||
MVP21: Onboarding flows for HAs | Descoped. But weirdly SAF-481 is labelled MVP1#21 and refers to user onboarding not HA onboarding | Clarify & tidy up Jira or spreadsheet. | MVP22: Safe Paths → Path Check | Believe in Test, but marked BLOCKED | Check Jira status||
MVP22: Safe Paths → PathCheck | R4T | |||||
MVP23: Rework HA YAML file | SAF-400. Will deliver alongside MVP7. | Jacob’s top priority - to deliver by end of day. | ||||
MVP24: Tab redesign | SAF-479. Ready for Test |